Sunday, 2 October 2011

more waiting...

Oh man, PCI isn't on the 5th! 

When we asked about when PCI is expected to be, SS communicated inspection 5th, so we thought yeah PCI! Buhbow...it's actually a building inspection.  The PCI is booked in for the 26th.  SO more waiting, waiting, waiting...

Went around this weekend and there's still a bit to do though:

- theatre door needs replacing
- painting of the void area by the stairs and dwarf wall
- repainting/patch painting of the areas that were needing to be rectified that didn't pass last inspection (i.e. cornicing, areas around windows or doors)
- bathtub needs to be installed
- plumbing in laundry needs rectifying.  It was plumbed to the left (if facing the trough) however we switched the washing machine space to be on the right side where the washing machine taps are....guh derr freddy!!!
- downpipes to be connected to stormwater
- shelving needs to be installed in cloakroom and wardrobes
- door handle to be installed on front door
- cupboard handles to be installed on those cupboards replaced because of error last month
- staining to be completed on stairs
- bulkhead above appliance tower needs to be completed
- tiling needs to be finished off around the kitchen island (as the correct cupboards have now been installed) and the bath hob and the splashback in the powder room needs to be rectified as installed incorrectly.
- tiling on balcony and terrace to be completed
- garage doors to be installed
- Modwood privacy screen on terrace to be installed
- carpets to be installed
- mirrors to be installed in all ensuites
- Showerscreens to be finished off (doors just need to be attached)
- Master ensuite window needs fixing as frame has come away from glass.
- misalignment of front door to be fixed up.  There is a noticeable gap towards the bottom of our door if you are inside looking out where you can see that the bottom part of the frame is bowed.


All the brick sills that weren't to standard have been replaced and they look heaps better.  The windows in the dining room and two awning windows that weren't square have been fixed up too so now it's not so noticable that they were out of line. 

Here's pics of our kitchen splashback, which has come up just as i imagined.  Loving it!

Splashback is in.  The photo comes up a lot redder than it actually is, which is a more raspberry tone.

Friday, 23 September 2011

The end is nigh...

How extremely exciting is it to see all those selections you picked nearly a year ago and had visions of in your head come to life.  Today Rob and I giggled like little kids in a candy shop to see our home so close to the finish line, with our PCI booked in for the 5th October!

And to think that all of this has happened in less than 25 weeks of build time (our site start date was 30/3/11 but the site cut etc didn't happen until late April)!

Way to go PD!  We received our final invoice (dated 30 sept) so i reckon they will give us this week to organise the final things like transferring water and electricity into our names, organise the final direct debit from our lender, etc.

Anyway, since our last visit on the 10th so much has been done.

- Most of the floor and wall tiles have been laid (just have to finish the batch hob and patches around the kitchen island) And also will have to fix up the splashback in the powder room as they laid the wrong tiles.  It should have been all feature tile but they laid it like the upstairs ensuite.
- Most of the faucets have been installed (plumber needs to just finish off the mixer taps in the master ensuite, install taps in the powder room and ensuite vanities)
- Spa bath needs to be installed :(
- The electricals have been finished off and all the lightswitches are installed.  Have to just go over the electrical plans to make sure nothing missing.
- Brickwork that needs replacing still to be done
- Paint patch ups required as they have come back to fix up the non flush items, such as windows and architraves.
- Carpet to be installed (approximately the 26th of September)
- Main door handle needs to be installed.

Here are some photos of our progress so far!


theatre - supposed to be three lights? will have to double check...

theatre cabling - lets see Robbie untangle these...

Living room

Galley - finally fixed their mistake

Laundry - oh beautiful laundry...how i hate to actually use you...but you're good to look at!! lol

Lounge room and dining room - can't wait to see the carpets go in!

Study - sunny spot to work in

Front door - lock on, can't wait to see the bar handle!

Powder room - need to get the splashback fixed up..should be all the feature tile! And the soft close toilet...lol

Return air duct - bloody bigger then i expected

Spa bath - I can't wait to use you!

Master Ensuite Shower - exactly the effect we were after!

Master Ensuite Vanity - now we just have to fight over which side is which!

Ensuite Shower - tiling came up good

Ensuite Vanities - A touch of bling

Kitchen - have to have a chat with the SS about the island bench lighting - not quite the placement we were after.

Laundry - nifty washing machine taps

Back of house - against the chill of the wind, the sun was warm and the family didn't get out of the way fast enough...lol

Entryway - can't wait until those stairs are stained!

Stairs - the dwarf wall doesn't look too bad

Saturday, 10 September 2011

Rendered Portico and Garage progress

Popped around this weekend to have a looksee at any progress on the house and to take my Granddad to see it.  Poor Pa has listened endlessly to Rob, mum and myself talk about the place but he hasn't even seen it!  He was a carpenter back in the day so it was good to hear that he thought the craftsmanship was good :)

The portico has been rendered and down pipes have been installed. 

The portico and moulding is going to be painted Magic Mocha.  Our garage door is going to be contemporary style in paperbark.

Here is an updated pic of our facade!


Thursday, 8 September 2011

Fixing to get to the end....

Been a while between blogs but there has been so much progress!!!  I have not gone around to the house for two reasons, 1. workload has increased which has taken a lot out of me at the end of the day and 2. i just wanna be in already and get impatient when i go onsite so best visit on the weekends so i can have a good surprise :)

Okay so fixing stage is now complete.  Our walls are beautifully painted (bar the wall along the stair (?)), internal doors have been painted and hung (there is the mystery of the disappearing theatre door of which i will explain later :P), stairs are installed, all cabinetry has been installed, waterproofing of the wet areas is complete, kitchen installed (with two errors which are in the process of being rectified), bifolds, laundry and front door stained (english walnut), skirting boards and architraves installed, tiles have been delivered and carpets are expected to be in on the 26th September.  It's near the finish line!

Back to the issue of the mystery door - about mid August we had delivery of all the internal doors.  Amongst them was our feature door for the theatre room, which is very simiilar to our laundry door shown below.  When i took the pics over the weekend, we saw a nice glossy flush panel attached to the door frame - no sign of the nice expensive corinthian door that should have been stained and hung there.  hhhmmmmm....Rob has spoken to our SS, just awaiting an update.

Also noticed the boxes for the dishwasher and cooker around the rubbish cage but no sign of the equipment.  They must deliver them there, unwrap and store elsewhere? Just seems wierd why they would unbox the units though...again, wierd.

Piccy time! There's a few..lol!



This is the before and after shot...pretty radical change :)
 
English Walnut stain on bifolds
Alfresco area

Bedroom 2

Bedroom 3

Dining Room

English Walnut Stain on front door.  Just a note to those that might be expecting a uniform colour of stain, this will be affected by the type of wood that is used in making the door.  Ours was a reddish type of wood (jarrah?) so that when our stain went on it has come up darker and more redder than i would have liked BUT i still like the overall look.  Can't help the characteristic of the wood.

Downstairs Powder Room

Stairs installed yet to be stained

Feature Niche

Garage - Roof tilers were there today (8/9/11)

Kitchen - two big boo boo's - forgot to include our hidden cupboard to the left of the issland bench and also placed the appliance tower in the wrong spot! Hope this gets rectified before tiling!

Galley Kitchen - notice tower location.  This should be on the opposite wall (mirror image)

Bedroom 4

View from top of stairs

View to Rumpus Room


Laundry all kitted out

Laundry Door stained English Walnut

Living Room and Kitchen

Lounge Room

MAster bedroom

Master ensuite

Rumpus Room

Study

Theatre Room

Tuesday, 2 August 2011

progress...gotta love it! Our build is really moving along at a fast pace.

We have now completed lockup, invoice received and paid last monday. 

Very happy with the workmanship of the brickwork (although it is still yet to be cleaned) and our bifolds and laundry door has been installed.

The insulation went in last week and the eaves have been put in. The plastering was to have commenced but as at yesterday it hadn't been done yet. The bath hob is in in our master! I am so impatient for that to go in! That is so going to be my lady land...lol...Rob can have the mancave below (AKA theatre room).

We were onsite weekend before last to check up on our garage/shed, and whilst there thought we'd check out how the "octopus in the roof" (AKA heating/cooling ducts) was going. 

Well, in the last post i had a photo that showed two black ducts in what would be the kitchen area.  We had cause for concern on that one as we weren't sure why there was a double up.  We had 10 ducts (5 upstairs and 5 down) and added an extra 1 in the store room.  If we counted up what we had onsite there was 12.  After relaying this to the SS, we were told that because of an engineering beam between the gallery/kitchen and dining room the duct couldn't go where it was supposed to in the dining so they moved everything over 2.5 metres.  Well that's all well and good, except that we didn't have a duct in the dining room in the first place and it still didn't explain the extra duct. 

After discussing with our SS that we didn't request a duct in the dining and did not want an extra in the kitchen, he investigated and it was found that the purchase order that was put through for the ducting was dated 17th Feb (the day after our contract signing) and which requested 12 ducts!  During contract we found where it was pricing for our heating/cooling they had doubled up on the extra that we requested (instead of being 10 plus an extra one it was put in as 11 and a note made further down about a duct in the storeroom which was counted again).

We picked this up before signing and our CSC made a notation and had clarified this with the drafting department and we made sure it was correct on the construction drawings we received on 28/3/11.  R scanned through the copy of construction drawings that we signed off on to the SS and all has been fixed up.

Just a note to all those starting to build, double check the construction drawing dates are consistent!

Another electrical error was picked up too.  It seems the power cable that should have been pulled through to our terrace hadn't and now it's sticking into bedroom three! R raised this with SS and he is going to check it out.  Know your electrical and construction plans inside and out guys!

And here are some progress piccies...



PORTICO!!!


Theatre Room - Insulated week commencing 25th

Dining and Lounge room - Insulated week commencing 25th

Terrace with cement sheeting down

My Bath Hob!!! Can't wait for that bath....

Bedroom 3 - Insulated week commencing 25th

hmmm, this should be on the other side of the wall...which is all bricked up...

Bedroom 2 - Insulated week commencing 25th

Rumpus Room - Insulated week commencing 25th

Bedroom 4 - Insulated week commencing 25th

Study - Insulated week commencing 25th